Project Overview

project name: Royal Alexandra Hospital – Paisley Energy Centre
quantity surveyor: Storrier & Donaldson
client: NHS Greater Glasgow and Clyde
services consultant: WGM Consulting Engineers
value: £2.8m
structural engineer: The Structural Partnership
architect: IDP
main contractor: Taylor and Fraser

Replacement of Steam Boiler Plant by providing a Biomass Boiler Plant.

Scope of Work

Removal of Redundant Steam Boiler Plant Installation Of Biomass Boiler Plant and associated Fuel and Ash Handling Systems

  • Phased removal of Existing Steam Boiler Plant
  • Installation of New Steam Boiler Plant Biomass and Conventional
  • Phased Replacement of Hot Well Tanks
  • Installation of RO Water Treatment Plant
  • Installation of Heliex Generator
  • BMS Controls
  • Civil and Builders Work
  • Flue Installation
  • Commissioning